The Dalles, Oregon
Why did Google build its first data center in The Dalles, Oregon?
The Dalles has sold the same thing since 1958: cheap power from the river. Aluminum bought it first. Google bought it next.
Google opened its first data center in The Dalles, Oregon, in 2006. Google says so on its own data center page, and The New York Times confirmed it in March 2025, putting the cost of that first facility at an estimated $600 million. The campus turned 20 in 2026, and the question it raises has only grown sharper: what does a small town trade for a piece of the cloud?
Power, fiber, and a code name
The Dalles sits about 80 miles east of Portland on the Columbia River, below a dam that has powered the town since the 1950s. When Google came looking in 2005, the town offered three things the company wanted: cheap hydroelectric power from The Dalles Dam, marketed by the Bonneville Power Administration; a large surplus of fiber-optic capacity left over from the dot-com buildout; and cheap land with tax breaks. The city had built its own fiber loop, QLife, with major construction finished in 2003, to attract exactly this kind of industry.
The project arrived under the code name Project 02, and the secrecy was real. City officials signed confidentiality agreements and could not comment. Diane Sherwood, executive director of the Port of Klickitat, told The New York Times in June 2006: "No one says the 'G' word." The Times put the story on its front page on June 14, 2006, with an aerial photo of two buildings, each about the size of a football field, with cooling plants four stories high. Local real estate prices had already risen 40 percent, and the town expected 60 to 200 permanent jobs in a town of about 12,000 people.
The dam made the town twice
The Dalles Lock and Dam was built from 1952 to 1957, with 22 turbine units and a nameplate capacity of 1,780 megawatts, according to the Army Corps of Engineers. It is one of the ten largest hydropower dams in the nation. The dam drowned Celilo Falls on March 10, 1957, when the gates closed and Lake Celilo filled. The falls had been an ancestral fishery of the Yakama, Warm Springs, Umatilla, and Nez Perce peoples for thousands of years, and $23.5 million was paid in compensation for lost treaty fishing rights.
The dam's power drew the first buyer. Harvey Aluminum opened a smelter in 1958, and the plant employed up to 500 workers at its height. Martin Marietta took it over around 1970. Fluorine emissions damaged nearby orchards, and orchardists sued at least 14 times starting in 1961. Production was curtailed in 1984, the site was listed as a Superfund site in 1987, and the plant wound down through the 1990s and closed by the early 2000s. Google bought the former smelter property in 2016 to build more data center buildings on it.
The Times said it plainly in 2006: Google was "a successor to the aluminum manufacturers that once came seeking the cheap power that flows from the dams holding back the powerful Columbia." That sentence is the spine of this story. The product changed. The bargain did not.
The water fight the town lost to its own newspaper
In September 2021, Oregonian reporter Mike Rogoway asked the City of The Dalles for Google's historical water-use records. The city refused, saying the figures were trade secrets. The Wasco County District Attorney ordered release in October 2021, and the city sued its own local newspaper to keep the records secret. The case was Wasco County Circuit Court Case No. 21CV40820, The Oregonian vs. City of The Dalles. It settled in December 2022, and the city released annual water-use figures back to 2012.
The released figures showed Google's water use had nearly tripled in five years. The city series put Google at 355.1 million gallons in 2021, roughly 29 percent of all the water the city used that year. Google's own series measures something different: 358.3 million gallons withdrawn, 83.8 million discharged, and 274.5 million consumed in 2021. The two series are not the same measurement, and this story does not mix them. The 2025 figures are still contested, with Google's own series at 469.0 million gallons consumed and the city metered series citing about 550 million, so this story claims only the settled 2021 figures.
The tax breaks are on the record too: Google received more than $240 million in tax breaks on its existing facilities over 15 years. Google also proposed spending $28.5 million to expand the city water system by five million gallons a day for two more data centers, approved by the city council in November 2021.
The boom is still live, and so is the drought
The Dalles is not a historical case. It is the live one. In January 2026, OPB investigated the city's push to expand a reservoir in the Mount Hood National Forest, drawing on water rights that came with the smelter land Google bought in 2016. Wasco County was in severe drought in early November 2026. Up to 5 gigawatts of new data centers are proposed along the Columbia River, and the International Energy Agency's April 2026 update put global data center electricity demand up about 17 percent in 2025, with a base case near 945 terawatt-hours by 2030.
The town has about 16,010 people by the 2020 Census, with a July 2025 estimate of 15,745. It is the county seat of Wasco County and one of the oldest permanently occupied places in Oregon, a Native trading center for at least 10,000 years. The dam, the smelter, and the data centers are three chapters of the same story: a place whose river power keeps getting sold to the next industry, while the town negotiates what it gets back.
What to do on a first visit
Start at the Columbia Gorge Discovery Center and Museum, 5000 Discovery Drive, the official interpretive center for the Columbia River Gorge National Scenic Area. Admission is $12 general, $10 for seniors 62 and older, $7 for ages 6 to 16, and free for ages 5 and under, per the official site. Winter hours run 10 a.m. to 4 p.m. until March, per the official site; other sources list 9 a.m. to 5 p.m. daily, so check before travelling.
Then go to The Dalles Dam Visitor Center at Seufert Park, 3545 Bret Clodfelter Way, off I-84 exit 87. Admission is free. The schedule conflicts across Army Corps sources, with some listing weekend-only hours in summer and others daily, so check the Corps schedule before travelling. Eagle Watch runs each January. The Fort Dalles Museum, at 500 W 15th St in the 1856 Surgeon's Quarters, is open daily 10 a.m. to 5 p.m. from April through November, and Friday through Sunday 11 a.m. to 4 p.m. in January and February. Admission is $10 for adults, $8 for seniors 60 and older, and $5 for children 5 to 17. The official site states no hours for March or December.
Sunshine Mill, a historic flour mill turned tasting room at 901 E 2nd St, is worth a stop, but its hours conflict across listings and its tasting fee is unverified, so check before travelling. The Google campus itself is not open to visitors and offers no public tours. Say so plainly to anyone who asks: the buildings and cooling towers are visible from public roads only.
Select a passage, then Share to send it with a link.
Questions, answered
- Why did Google choose The Dalles?
- Cheap hydroelectric power from The Dalles Dam, a large surplus of fiber-optic capacity from the dot-com buildout, cheap land, and tax breaks. The city had also built its own fiber loop, QLife, to attract the industry.
- When did Google open its first data center in The Dalles?
- In 2006. Google calls it its first data center, and The New York Times confirmed the 2006 opening and an estimated $600 million cost in March 2025.
- How much water does Google use in The Dalles?
- The city series released after the 2022 court settlement put Google at 355.1 million gallons in 2021, roughly 29 percent of all city water use, nearly triple the 2017 figure. Google's own series measures consumption differently, at 274.5 million gallons consumed in 2021. The 2025 figures are contested and are not claimed here.
- Can you visit the Google data center in The Dalles?
- No. The campus is a secured industrial site with no public tours. The buildings and cooling towers are visible from public roads only.
- What happened to the aluminum smelter?
- Harvey Aluminum opened the smelter in 1958. It was listed as a Superfund site in 1987 and wound down through the 1990s, closing by the early 2000s. Google bought the former smelter property in 2016.
Sources
Checked November 17, 2026.
- Google: The Dalles data center location, first data center, 2006
- The New York Times, Mar 16, 2025: 2006 opening, $600 million estimate (read via mirror; confirm against NYT archive in verification)
- The New York Times, Jun 14, 2006: Project 02, secrecy, fiber surplus, aluminum successor (read via mirror; confirm against NYT archive in verification)
- U.S. Army Corps of Engineers: The Dalles Lock and Dam fact sheet, 22 units, 1,780 MW
- The Oregonian, Dec 18, 2022: water use nearly tripled, 355.1 million gallons in 2021, 29 percent of city use
- Data Center Dynamics, Nov 2021 and Dec 2022: lawsuit, tax breaks over $240 million, $28.5 million water proposal
- OPB, Jan 23, 2026: reservoir expansion fight, smelter water rights
- Oregon Encyclopedia: The Dalles, hydropower and fiber, smelter dates
- EPA, Fifth Five-Year Review: Former Martin Marietta Reduction Facility, Superfund 1987
- U.S. Census Bureau, QuickFacts: The Dalles population 16,010 (2020), 15,745 estimate (2025)
More to read
- Cottonwood’s chocolate shop began in a Michigan kitchen
The Michigan kitchen behind a Cottonwood chocolate shop, with truffle fillings to explore and a box to take home.
- A bookshop with a life after the last page
A bookshop that still acts like a small arts institution. Open daily in the Saint George lobby, with a gallery show on the record in June 2026.
- A quieter night under St. Augustine’s lights
More than three million white lights, free, over the oldest city in the country. Go on a weeknight, park once, and walk.